| |
Shatin Town Hall Plaza
Date of Commencement: January, 2008
Anticipated Date of Completion: July, 2008
Main Contractor: Teamfield Building Contractors Ltd.
Consultant: JCL Consultants Ltd.
Architect: Sun Hung Kai Architects & Engineers Ltd.
Client: LCSD
|
| |
Sewage Plumbing Station, No. 2 Lantua Island, Hong Kong (愉景灣)
Date of Commencement: February, 2006
Date of Completion: July, 2006
Main Contractor: N/A
Consultant: Parsons Brinckerhoff (Asia) Ltd.
Architect: N/A
Client: Hong Kong Resort Co. Ltd.
|
| |
Hong Kong Movie City, Tsueng Kwan O, Area 106 TL67 & 81, Sai Kung (香港影城)
Date of Commencement: February, 2003
Date of Completion: July, 2004
Main Contractor: China Overseas Building Construction Ltd.
Consultant: Parsons Brinckerhoff (Asia) Ltd.
Architect: Wong Tung & Partners Limited
Client: Hong Kong Movie City Co. Ltd.
|
| |
Sewage Treatment Plant at Ma Wan Island
Date of Commencement: April, 2000
Date of Completion: April, 2002
Main Contractor: Gamfield Construction Co. Ltd.
Consultant: Meinhardt (E&M) Limited
Architect: Simon Kwan & Associates Ltd.
Client: Ever Fast Limited
|
|
KMB Bus Depot at West Kowloon Reclamation
Date of Commencement: November, 2000
Date of Completion: November, 2001
Main Contractor: Dragages at Travaux Publics (HK) Ltd.
Consultant: J. Roger Preston Limited
Architect: Sun Hung Kai Engineering Co. Ltd.
Client: Kowloon Motor Bus (1933) Ltd.
|
| |
275 / 11kV Zone Substation at Connaught Road, Central
Date of Commencement: March, 1996
Date of Completion: April, 1997
Main Contractor: Nishimatsu Construction Co. Ltd.
Consultant: The Hong Kong Electric Co. Ltd.
Architect: Hsin Yieh Architects & Associates Limited
Client: Hong Kong Electric Co. Ltd.
|
| |
MTR Depot at Tsuen Wan
Date of Commencement: July, 1995
Date of Completion: March, 1997
Main Contractor: Junic Construction Co.
Consultant: Meinhardt (E&M) Limited
Architect: Hassell Limited
Client: MTR Corporation
|
| |
Component & Avionics Overhaul Facility for HAECO at Tsueng Kwan O
Date of Commencement: January, 1996
Date of Completion: December, 1996
Main Contractor: Chun Wo Construction Co. Ltd.
Consultant: Meinhardt (E&M) Limited
Architect: Pekko Engineers Limited
Client: Hong Kong Aircraft Engineering Co. Ltd.
|
| |
Western Harbour Crossing (西區海底隧道)
Date of Commencement: June, 1995
Date of Completion: June, 1996
Main Contractor: Nishimatsu Construction Co. Ltd.
Consultant: Maunsell Consultant Asia Ltd.
Architect: RMJM Hong Kong Limited
Client: Western Harbour Crossing
|
| |
Reprovisioning of Cheung Sha Wan Shipyard to Stonecutters Island North
Date of Commencement: January, 1993
Date of Completion: July, 1993
Main Contractor: Kam Wo Construction Co. Ltd.
Consultant: J. Roger Preston Limited
Architect: Ho & Partners Architect, Engineer & Development Co. Ltd.
Client: The Six Shipyard Companies
|
| |
Victoria Road
Date of Commencement: October, 1990
Date of Completion: October, 1991
Main Contractor: Winner Engineering Co. Ltd.
Consultant: Rocco Design Limited
Architect: Rocco Design Limited
Client: N/A
|